Dr. Hal Weinberg Spirit Park Expansion
Dr. Hal Weinberg Spirit Park is located at 1009 Ravenswood Drive in Anmore, adjacent to the Anmore Community Hub at 2697 Sunnyside Road.
The Dr. Hal Weinberg Spirit Park Expansion will enhance Anmore’s primary outdoor gathering space with improved recreation opportunities, expanded parking, new gathering spaces, and stronger connections between the park and the Anmore Community Hub.
Following community engagement, Council direction, and detailed design, construction of the project is set to begin in late August 2026.
This page provides project information, construction updates, project milestones, and key documents.
Project Overview
The Dr. Hal Weinberg Spirit Park Expansion is a multi-phase capital project that will improve access, connectivity, and recreation opportunities while preserving the park’s role as Anmore’s primary community gathering space.
The project includes:
- A new Ravenswood Drive road alignment
- Expanded parking, including accessible and electric vehicle parking
- Improved pedestrian connections between Spirit Park and the Anmore Community Hub
- A community plaza for events and gatherings
- Upgraded pathways and landscaping
- New park amenities informed by community engagement
View the preferred park drawings approved by Council: anmore.com/park-expansion-preferred-drawings.
Project Updates
Construction Updates
Construction of the Dr. Hal Weinberg Spirit Park Expansion started in late August 2026, starting with prep work for the Ravenswood Drive realignment and parking lot improvements.
Ravenswood Drive is now anticipated for partial closure beginning October 1, 2026. This timeline is subject to change due to ongoing construction coordination and engineering updates to the road alignment and regrading.
Tree removal and replanting are required to accommodate the new road alignment, park improvements and regrading. Some trees within the construction area are scheduled to be removed during the week of September 22, 2026. Dr. Hal Weinberg Spirit Park will be fenced off during this phase. Read the construction updates below for more details, which also includes the latest construction notices and traffic impact maps.
If you have questions about construction or temporary traffic changes, please contact Ike DeBoer, Construction Reviewer with ISL Engineering and Land Services Ltd. by phone 604-307-2002 or by email icdeboer@shaw.ca.